Route 1 Milling and Resurfacing Project
The State of Connecticut has scheduled a milling and resurfacing project for Route 1 from the Hammonasset Connector to the Clinton town starting on June 5, 2022.
- The tentative start date for the MILLING portion of this project is scheduled to begin the night of Sunday, June 5, 2022, continue for approximately two (2) nights of work ending the morning of Tuesday, June 7, 2022.
- The tentative start date for the PAVING portion of this project is scheduled to begin the night of Wednesday, June 15, 2022, continue for approximately two/three (2/3) nights of work ending the morning of Friday, June 17, 2022.
~For both portions of this project the work hours will be from 7:00 p.m. through 5:30 a.m. each night of work.~
*NOTE: Adjustments to this schedule will be necessary due to inclement weather.