Posted on: August 17, 2015

August 17, 2015: CT DOT Permit

Update: Monday, August 17, 2015
CT DOT has not yet released the necessary Encroachment Permit
The Town of Madison and the DOT are working to resolve several design elements. Town Administration have devised a plan to have these issues, which include a repaving request by the State and request that the project not use Vehicular Grade Pavers for the crosswalk resolved ASAP. Residents will note that underground utilities were recently marked with paint on the pavement and sidewalks – the contractor has made additional markings to allow for a quick start. Check back for more details this week.