Posted on: March 11, 2016

Downtown Construction to Restart Monday, March 14

downtown Webcam

A mild winter will allow the Madison Center Project to resume construction on Monday, March 14.

Town Engineer, Mike Ott confirmed today that construction on the second part of Phase 1 will begin Monday. It is expected that demolition of the old sidewal...Read on...

Posted on: November 25, 2015

Chamber and EDC Acknowledge 2 Individuals at Project Ceremony

Main St

Just in time for the increased traffic flow, the Madison Center Project has completely moved off of main street and the sidewalks as Madison center is decorated and readied for the holidays. The Economic Development Commission reports that the constructio...Read on...

Posted on: November 12, 2015

Final Week of Center Project Phase 1

lightpole and bricks

Major construction will wind-down this week for the Madison Center Project. While weather conditions weren’t as cooperative this week as they have been for most of the project, but the contractors have still made significant progress installing the brick ...Read on...

Posted on: October 30, 2015

Another Fuel Tank Discovered

downtown fuel tank and pavers

Brick pavers are being laid at a brisk pace on the north side of Main Street. Brick pavers can now be enjoyed from Wall Street heading west to in-front of the “2000 Building”. As construction has edged westward, parking spaces have been opened. There are ...Read on...

Posted on: October 23, 2015

Parking Spaces in Front of Theater and Post Office Expected to Reopen – Brick work completed in fron

Parking Spaces in Front of Theater and Post Office Expected to Reopen – Brick work completed in front of USPS

The pace of the Madison Center Project continues to benefit from excellent weather conditions and an efficient construction crew. Brick paver ...Read on...

Posted on: October 9, 2015

Brick Pavers Delivered, Installation October 12th

Oct 9, 2015: Brick Pavers Delivered: Installation to Start Week of October 12 Clay brick pavers were delivered to Madison Center this week and will be installed soon. Visitors to downtown Madison this past week may have noticed the pallets of bricks being...Read on...

Posted on: October 5, 2015

Downtown Parking Lot Construction Starts

downtown parking

Construction started this morning on the municipal parking area behind the movie theater and Madison Coffee Shop. The construction has resulted in partial closure of the lot, leaving about half of the lot open to municipal parking. The construction of the...Read on...

Posted on: September 21, 2015

New Curbing

UPDATE: September 21, 2015 New Granite Curbing The new granite curbing was laid from Wall Street along the north side of main street to the eastern edge of Café Allegre as the contractor has been concentrating construction work on the eastern half of the ...Read on...

Posted on: September 13, 2015

Parking Information

UPDATE: Sept 13, 2015 Parking Information The Madison Center Project will begin the process of curb and sidewalk removal the week of September 14. As construction proceeds, the contractor will be storing equipment in the Town owned municipal parking area ...Read on...

Posted on: September 11, 2015

Sep 11, 2015: First Weeks

UPDATE: Sept 11, 2015 First Week of Madison Center Project a Success; Here’s What’s Next The first week of the Madison Center Project construction was a success. During the initial week, diseased and dead trees were removed and the pavement along Route 1 ...Read on...

Posted on: September 8, 2015

Sep 8, 2015: Tree Removal

UPDATE: Sept 8, 2015 Trees Removed from Madison’s Downtown Residents and visitors to Madison’s downtown might notice something missing: trees. Many of the trees downtown were removed Tuesday as the Madison Center Projected kicked off. The removal, which s...Read on...

Posted on: September 5, 2015

Sep 5, 2015: Construction to Begin Sep 8

Last Image before construction begins

In a meeting at Town Campus on Friday morning, Town Engineer Mike Ott presented the construction schedule for the Madison Center Project to First Selectman Fillmore McPherson, EDC Chair Ryan Duques and Chamber of Commerce Executive Director Eileen Banisch...Read on...

Posted on: August 17, 2015

August 17, 2015: CT DOT Permit

Update: Monday, August 17, 2015
CT DOT has not yet released the necessary Encroachment PermitThe Town of Madison and the DOT are working to resolve several design elements. Town Administration have devised a plan to have these issues, which include a r...Read on...

Posted on: July 17, 2015

July 17, 2015 Phased Design

Town officials have updated the construction plans under the new Phased Design, which was approved by the Board of Selectman and Board of Finance in late June. ** Construction start is imminent as the town awaits a final Encroachment Permit to be issued b...Read on...

Posted on: July 1, 2015

July 1, 2015 MCP Ground Breaking


Governor Malloy and First Selectman McPherson break ground for the Madison Center Project to begin.

View More on Facebook

Posted on: October 7, 2016

Construction Notice

The pavement milling of Lovers Lane is scheduled to begin on October 11th. One lane of alternating traffic will be maintained at all times in work zones.

Posted on: October 5, 2016

Skate Park Closed

The skate park at the Madison Arts Barn has been closed due to preparation for construction of a new emergency communications tower, which will be located on the current skate park site. The Town of Madison and the Beach & Recreation Department are w...Read on...

Posted on: October 24, 2016

Limited Voter Registration Session

The Registrars of Voters will hold a Limited Voter Registration Session on Monday, November 7, 2016 between the hours of 9:00 AM and 5:00 PM at the Registrars’ Office at the Madison Town Campus. Only Members of the Armed Forces on active duty or who have ...Read on...

Posted on: October 17, 2016

Voter Registration Session

The Registrars of Voters will hold a Voter Registration Session on Tuesday, November 1, 2016 between the hours of 9:00 AM and 8:00 PM at the Registrar’s Office at the Madison Town Campus. This is the last day for persons whose eligibility to vote based on...Continue...

Posted on: August 31, 2016

From the First Selectman’s Desk

From the First Selectman’s Desk
We got a $500,000 STEAP Grant to build the Strong Center Field Houses in late February, but if you go down to the Surf Club today, you’ll see that they’re not done yet. This is disappointing to me because my goal was to h...Read on...

Posted on: June 1, 2016

Gov. Malloy Reminds Residents Atlantic Hurricane Season Has Begun

Residents Advised to be Prepared for Any Severe Weather

(HARTFORD, CT) – With the first day of the 2016 Atlantic Hurricane Season beginning today, Governor Dannel P. Malloy and stat...Read on...

Posted on: January 6, 2016

Capital Improvement Program

At the heart of the Capital Improvement Program is a planning process that 1) identifies the capital needs of the Town, 2) develops estimates of costs for the preservation (or non-recurring maintenance),enhancement, replacement, acquisition, and construct...Read on...

CIP Webpages & Additional Information